Ok now for one of my killa questions,, a price check! i no i no but i dont have any one else to ask..
here is hows i see this job workin out -
Avarage livin room
-----------------------
skim 4 walls with 2 windows and fireplace and chimny breast is back to brick.
Day 1 - set up bond it to all walls set beads on windows and fire place,scrach coat fire place and breast and maybe skim a wall.
Day 2 - Top coat fireplace, skim the rest of room
Day 3 - skim chimny breast, clean away and get rid of rubbish..
materials £200 ish
Me 3 days £150 a day =£450
lab £60day x2days = £120 (give lab 50 cash)
= £770..
IS THIS TO HIGH? I CANT HELP FINK IT IS!plus the hole house will need doing over the year so..
thanks for any guid