Sorry new build in brighouse there's around 1000 sqm ov board and skim I need 5 good plasterers if we can finish the job in ten to twelve days i will pay £150per day just like all of us time served lad's should be on
Sorry new build in brighouse there's around 1000 sqm ov board and skim I need 5 good plasterers if we can finish the job in ten to twelve days i will pay £150per day just like all of us time served lad's should be on
if we can finish the job in ten to twelve days i will pay £150per day
I'd still struggle wiv that5 or 6 plasterers 10-12 days = 60-72 man days to board and set a 1000m2.
Thats 14m2s a day per man complete= 4.5 boards tacked and skimmed.
@superspread @theplasterman
What Time we starting tomorrow?.
You wouldn't answer your phone for 150 Scotty5 or 6 plasterers 10-12 days = 60-72 man days to board and set a 1000m2.
Thats 14m2s a day per man complete= 4.5 boards tacked and skimmed.
@superspread @theplasterman
What Time we starting tomorrow?.
Nor uYou wouldn't answer your phone for 150 Scotty
Sorry late getting back today...was knackered from all me jobs yesterday..i think this would be a good job to jump on.To be fair I been doing 79-81.75m2 a day on me own the last few weeks on the run upto Xmas but would be more than happy to do the day rate in the new year.5 or 6 plasterers 10-12 days = 60-72 man days to board and set a 1000m2.
Thats 14m2s a day per man complete= 4.5 boards tacked and skimmed.