gooner59
Private Member
Well back home now ! just got started in north london then got the call to go over to Cobham ,when i got there they needed the pool tiled and grouted and filling -up in three days !!!!!!!!!! as they are having an invitations only viewing day today so i got stuck in tiled all walls and grouted day one !! day two tiled floor/grouted no pressure here !!! ,by this time i had spectators as nobody had seen so much work done by one person LOL third day steps/grout and finish, i did worn them that it was against the guarantee to fill the pool so soon but the hose pipe was in the pool friday night day three!! i then crashed the night in the hotel then came home this morning to walk my poppy, lets hope the cheque is in the post ...........lol