excuse my ignorance but never seen or done .i have a damp job to do and am i right in thinking if it s tanked its pretty full proof.how do you apply tanking etc etc cheers lads
Also forgot to mention you cant apply the tanking the same day the first coat of render goes on so its a few days process best to render one day tank the next then top the day after.bodplasterer said:If its vandex or some simalar type you have to sandwich it between render so put a coat of render on dont worry too much about how flat it is apply the tanking by brush (you usually need to have a fillet to the floor and coat that with vandex) when applying the vandex also try and stipple it so the next coat will have a key and then the rest is just normal float coat and skim