Hi guys , just wondering what everyone usually does with sand and cement . I usually start with 4-1 for the dubbing out and then the first coat ( same day) then finish coat of 5-1 just wondering is that ok ? I know some boys do a 4-1 for the first two coats and the finish ? Just want to know what's best ? Thanks
 
Hi guys , just wondering what everyone usually does with sand and cement . I usually start with 4-1 for the dubbing out and then the first coat ( same day) then finish coat of 5-1 just wondering is that ok ? I know some boys do a 4-1 for the first two coats and the finish ? Just want to know what's best ? Thanks
It depends on the background, brick or block that's solid will be suitable for 4/1 mix, thermalites would be suitable for 6/1 scratch, it also depends on whether you scud or sbr scud etc. floating coat is best at least a week later, keeping sure that the scratch doesn't excessively dry out in hot weather either by covering or dampening down
 
Plus bad idea (I'm not bothered either way) you turn up at my house my dogs will have a field day with you :rolleyes) but I'll meet you wherever ??
 
@church sorry pal but this numpty has pinched pics of my work saying he did it and I've had enough and asking where he is so I can meet him face to face and sort it out!?
 