Are all your videos on you tube or on your site?The principal is based on mixing any bagged gear.
Add correct water to mixing pot or bucket
Gently add powder
Turn on whisk or machine
Check consistency increase or decrease water
Carry to spot or connect pipe
Lay on wall or point gun and spray
Repeat process until complete
Maybe more videos of setting up the equipment and getting it ready to spray could be helpfull
A pft app would be good for newbie user's.
When I bought the ritmo Ian sent me a set up list which we used for the first few weeks which was good
Yes a few years now john.
We always work out of a water butt now ,run the water pump on the G4
G5 have a built in water pump so u have to have a butt next to the machine. I dont like that set up personally and prefer to run a machine with a Av300 water pump set up away from the machine. You can pump water from the av300 up to 25-30 mts away.
MAINS !!!!!!! Try Taylor Wimpey sites don't think they've heard of mainsWe run off mains water 95 % of the time never have any trouble in fact we have less as its 1less thing to worry about.
Did a site in Warrington the other week we had 70m of pipe from the mains and still rock steady.
Water at the machine chamber between 300 and 400 isn't a lot, I wouldn't say it was a trickle but it's not loads
MAINS !!!!!!! Try Taylor Wimpey sites don't think they've heard of mains
Having a diesel machine we've noticed a saving of about £50.00 a week on fuel,by using a drop of the red stuff on site.With the saving on rotor and staters as well it's a bit of a no brainer
Funny that isn't it. What does every building site require. Water, power and access. What do most of them have.
Well over 2000m2 and still plenty left on itHow long the rotors last then
i remember your concerns ,when you first got a G4 ,good to see things have worked out for you ,i know you do some very large contracts ,nice to know a g4 is good enough for your work load !This again lol
well I started out with a diesel ,sp11 lovely machine not a single worry about pumping distance but what a bitch to clean the thing was caked and I can't stand that.great for house bashing on a large site but no good for single houses ,we now have 2 g4s and I must say what a great machine ,I also think we could beat any diesel gang with the same amount of men ,anyone up for a race
This again lol
well I started out with a diesel ,sp11 lovely machine not a single worry about pumping distance but what a bitch to clean the thing was caked and I can't stand that.great for house bashing on a large site but no good for single houses ,we now have 2 g4s and I must say what a great machine ,I also think we could beat any diesel gang with the same amount of men ,anyone up for a race
Also on the memo can you please put don't get the renderer on site until your ready instead of when you think it's f!!!ing ready lol
All good mate at my end ,glad your doing well mateHi keith
yes mate the pump has worked out well ,so well I've just bought a second 1
the large contracts have now turned more into mainly one off self builds which I prefer but real busy with them so the g4 is perfect
how things with you,busy I hope if not ive got a few waiting lol
have they dug a trench in front the front door and all the way down the side right where you would put a hop up
I got to a job on wednesday ,agent says where you starting? I said only thing im starting is my engine ,im off ring me when scaffold is sorted.Just turned up on a job this week they were screaming for.
Me
"Where's the scaffold"
Them
"We took it down"
:banghead::banghead::banghead: