STO have sent the wrong beads , there customer service was not good ,it would double the cost to dub out with armat , i knew very little about there system tbh , they sent 10mm drips and 6mm stops . They then said the total thickness was only 4mm for both coats . So every thing was set up wrong before we knew .cant you just use aramat classic to doit?
The builder wants to use k rend uf base , as there have some over from another job .Sure you will need to use a specific STO product… their board is a bit unique, don’t use a cement based product on it!
cant you just change beads then?STO have sent the wrong beads , there customer service was not good ,it would double the cost to dub out with armat , i knew very little about there system tbh , they sent 10mm drips and 6mm stops . They then said the total thickness was only 4mm for both coats . So every thing was set up wrong before we knew .
If they’ve sent out wrong items then the cost should be on them to return and replace the wrong items. Fcuk dubbing out with classic to 10mm it would bankrupt the job lolSTO have sent the wrong beads , there customer service was not good ,it would double the cost to dub out with armat , i knew very little about there system tbh , they sent 10mm drips and 6mm stops . They then said the total thickness was only 4mm for both coats . So every thing was set up wrong before we knew .
Allready fixed and stuck on meshed on im afraidcant you just change beads then?
6mm stops and mesh anglebeads?
sto are shite
The builder wants to use k rend uf base , as there have some over from another job .