I am using the 4x1 to form the bays is that ok
I have 90 square ms of concrete to lay at a depth of 4" I am going to use 4x1 sawn for the shuttering what is the maximum size bays I can put the shuttering at I wil put in steel mesh if needed as I don't want it to crack the base is to take up to 4 cars
Fibres or steel pins pal saves u getting the nips out for the mesh 150 of crush whacked then visqueen b4 u pour.I have 90 square ms of concrete to lay at a depth of 4" I am going to use 4x1 sawn for the shuttering what is the maximum size bays I can put the shuttering at I wil put in steel mesh if needed as I don't want it to crack the base is to take up to 4 cars
I wouldn't concrete all in one day it would be done over 2 days the area is approx 10m x 3.8 wide if I break it up into 4 manageable bays making the shuttering with 4x1 and putting in reinforcement so the bays would be 3.8 x 2.5 with a edgeing trowel finish also the drive is on a slope would there be a problem with the concrete slumping down just curious how it will turn out