PhilPlaster said:
Im on my own at the mo and only charge for a plasterer plus materials. Do you reckon i should start chargin extra for labourers services as im doin the lot?
im guessin youre jokin here yes?
but just in case youre not, you PRICE for the JOB...
if it was 1 room and 1 room would take you on your own 1 day then youd charge say 2-300 quid...
if you had a labourer and you did it it 1/2 a day would you then charge 350 quid? for the same job?
the point of having a labourer is to make life easier for you, its your choice, when i take a labourer they start off doing next to jack but after a while theyre trowelling up etc, no point em sittin still unless theyre a complete and utter waste of space in which case whats the point? that way i get the job done quicker, say 1/2 a day quicker, which to me is 1/2 a day of MY RATE... I pay the labourer a LABOURERS rate, that means I make more money per hour spent on site and the customer gets a quicker cleaner job (tip - clean up yourself while the lab final trowels, youll be hard pushed to find a labourer that cleans up as well as you but they love to feel part of the 'team' by having a trowel in their hand)