Hi...
Been plastering for seven years... a job has come up to re render an extension about 35m2..
Just wondering if anyone could give me a guideline on quantities needed for materials?
Sand... is sharp sand best for both coats or is it better to use plasterers sand for the top coat? and how much.. would a tonne bag do it do you think?
Cement... any idea how much I'll need to cover 35m2
Lime.. how many bags and do I use it on both coats or just the top coat?
Also... They want a kind of pebble dash finish.. but its more like rough cast... needs to match old render..as its being blended in... probably need to have a play around with that really...
What's the best mix for doing that.. any ideas?
Be great if someone could answer all these questions so that I can get the price in and get cracking.. Nice one guys!
Been plastering for seven years... a job has come up to re render an extension about 35m2..
Just wondering if anyone could give me a guideline on quantities needed for materials?
Sand... is sharp sand best for both coats or is it better to use plasterers sand for the top coat? and how much.. would a tonne bag do it do you think?
Cement... any idea how much I'll need to cover 35m2
Lime.. how many bags and do I use it on both coats or just the top coat?
Also... They want a kind of pebble dash finish.. but its more like rough cast... needs to match old render..as its being blended in... probably need to have a play around with that really...
What's the best mix for doing that.. any ideas?
Be great if someone could answer all these questions so that I can get the price in and get cracking.. Nice one guys!