Risk

Members online

John j

Mono Don
Was thinking of putting under these steps on today bout 2pm. Scratch bout 9 in morning. Think it's a big risk. Only going on 10mm. It's got base coat on
20191018_093120.jpg
 
How about you are taking the piss .
How about get a pro to build them-fookin steps & then no need for that shitty render, will be filthy stained in no time

Your welcome
 
Is that wall built upside down? facing bricks out the ground with engineers on top.
case for the brickie police?
 
The brickwork might be right as the top brick looks like engineering. Being under the slab its going to absorb water if the slabs and joints are porous so will take a bashing in frosty weather. Done the same on my own property.

But as to timing? Overnight is fine if it is going to be dry but being where it is it will soon stain and could even fail. No drip on the steps and within 150mm of the ground etc etc.
 
Top