kirk johnstone
Private Member
nelly said:I have found when its hard to work out a price is to try to work out how long it will take me, divide that by a day rate and see how it stacks up.
Example - 200m2 of work, lets say £15 a meter = £3000
Then I look at it and guess at how long it will take.
Lets say I reckon 9 days at £150 a day, per man, for a 2 man team.
That comes in at £2700
I would say that £15 per m2 is about right in this case.
Some jobs are naughtier than others though, just doing the reveals on a full house can account for a full days work.
And even though most builders think fairies come in at night and put all the beads on for you, we know that is not the case, you can spend the equivalent of a full day just beading up a full house, whether its internal or external.
Apparently the midnight goblins put scrim on too
thanks mate thats all i wanted to know